- Project Title
- Carbon Filter Installation and Relief Stack Modification
- Project Summary
- The project involved the design development of a new carbon filtration system to be installed between the existing Cyclone Fan and the associated relief stack to atmosphere.
- The objective was to integrate the new carbon filter into the existing operating plant while retaining the required process flow path and accommodating the surrounding infrastructure.
- DMD was appointed to deliver the piping, mechanical, civil and structural design elements, with EC&I works undertaken separately by the client or other appointed parties.
- The design included modifications to the existing pipework and ductwork, development of the new equipment arrangement, supporting infrastructure and the civil foundation required for the filter installation.
- Sector
- Industrial Process Manufacturing
- Air Emissions and Filtration
- Project Location
- Client Challenge
- The client required a new carbon filter to be incorporated into an existing relief system between the cyclone fan and the atmospheric discharge stack.
- The new equipment had to be positioned within an established operational area containing existing pipework, ductwork, structures and plant infrastructure.
- Existing pipework and duct routes required modification to accommodate the filter while maintaining a practical and coordinated flow path.
- The arrangement needed to provide suitable support for the new and modified systems, together with safe access for operation, inspection and maintenance.
- Piping, mechanical and structural interfaces had to be coordinated with EC&I works being delivered by the client or other third parties.
- DMD Scope of Work
- Laser scanning and point-cloud data processing
- Site surveys and existing-condition verification
- Development of the equipment and ductwork routing
- Redesign of existing ductwork to accommodate the new installation
- Mechanical integration of the carbon filter with the existing cyclone fan and relief stack
- Secondary steelwork and supporting infrastructure design
- Civil foundation and equipment-base design
- Engineering Disciplines
- Project Delivery Approach
- A laser scan of the project area was completed and processed to establish an accurate record of the existing installation.
- Site surveys were undertaken to verify existing equipment, pipework, ductwork, structural interfaces and available installation space.
- Existing systems were redesigned where required to accommodate the new filtration equipment.
- Pipe and duct support requirements were developed alongside the routing to ensure the proposed arrangement could be safely supported.
- The civil base and structural elements were coordinated with the equipment loads and proposed installation arrangement.
- Key Engineering Features
- Installation of a new carbon filter within an existing relief system
- Integration between Cyclone Fan and the atmospheric relief stack
- Modification of existing pipework and ductwork
- Brownfield installation within an operational process area
- Coordinated equipment, piping, ductwork and structural layout
- Civil foundation design for the new filtration equipment
- Structural support and secondary steelwork design
- Coordination with separately delivered EC&I works
- Design for safe operation, inspection, access and maintainability
- Key Deliverables
- Coordinated 3D design model
- Equipment layout
- Pipework and ductwork general arrangements
- Secondary steelwork details
- Civil equipment-base design
- Technology and Software Used
- 3D laser scanning
- Autodesk Plant 3D
- Autodesk Navisworks