1. Project Title
  • Dock Water Cooling System Upgrade ($2.8M)
  1. Project Summary
  • The project involved the replacement and upgrade of the dock water system used to provide process cooling across the operational plant.
  • The existing centrifugal pump and filtration equipment had suffered major failures approximately 18 months earlier and had been replaced by a temporary rented submersible pump and Amiad filter.
  • The temporary arrangement was not suitable as a permanent seawater installation and presented an ongoing operational reliability risk.
  • DMD developed the design for a permanent duty/standby system comprising two new submersible pumps and two seawater-rated Amiad filters, connected to the existing heat exchangers.
  1. Sector
  • Animal Feed Manufacturing
  • Process Utilities
  1. Project Location
  • North West England
  1. Client Challenge
  • Dock water is used as a primary cooling medium for the plant, meaning a continuous and reliable supply is essential to maintain production.
  • The new equipment had to be installed and integrated without interrupting the existing temporary cooling arrangement.
  • DMD developed a phased design and installation strategy that allowed the majority of enabling works to be completed while the plant remained operational.
  • Final connection spools and system changeover activities were planned for completion during a controlled shutdown period.
  1. DMD Scope of Work
  • Laser scanning and site surveys
  • Targeted as-built verification of the existing installation
  • Equipment and piping layout development
  • Large-bore piping design and detailing
  • Civil and structural platform design
  • Secondary steelwork and pipe support design
  • Phased construction work packs
  • Multidisciplinary design coordination
  1. Engineering Disciplines
  • Piping
  • Civil
  • Structural
  1. Project Delivery Approach
  • A detailed laser scan and site verification exercise was completed to establish an accurate representation of the existing installation.
  • Equipment layout and piping route studies were undertaken to determine the most practical arrangement within the available quayside area.
  • Operational continuity was maintained by developing the replacement system around the existing temporary installation.
  • Access, maintenance, lifting, installation and future equipment replacement requirements were considered throughout the design.
  • Enabling and construction packages were developed to maximise the work completed while the plant remained operational.
  • Final tie-ins and system changeover activities were limited to a controlled shutdown window.
  1. Key Engineering Features
  • Duty/standby seawater pumping and filtration arrangement
  • Integration with existing heat exchangers and cooling infrastructure
  • Installation within a congested brownfield quayside environment
  • Complex large-bore piping routes within restricted space
  • Live-plant process and utility tie-ins
  • Coordinated civil, structural and piping design
  • Structural access and maintenance platform design
  • Seawater-compatible equipment and material selection
  • Design for safe operation, access and maintainability
  • Detailed planning of enabling, shutdown and changeover activities
  1. Key Deliverables
  • Coordinated 3D design model
  • Equipment and piping general arrangements
  • Piping fabrication isometrics
  • Civil construction details
  • Structural drawings
  • Secondary steelwork and pipe support details
  • Material take-offs
  • Demolition and enabling work packs
  • Phased construction packages
  1. Technology and Software Used
  • Autodesk Plant 3D
  • Autodesk Navisworks
  • 3D laser scanning and point-cloud technology